Where AI Can Create Value in Construction Operations

The strongest near-term case for AI in construction is in the paperwork around the work, not the work itself. A five-test screen shows why.

Executive summary

Construction has two problems AI is often pitched against: decades of flat labor productivity and a persistent shortage of people. Yet adoption is thin. In a 2025 RICS survey of more than 2,200 professionals, 45 percent reported no AI implementation and under 1 percent reported organization-wide use. This article asks which construction workflows have credible automation potential today. It proposes the Construction Workflow Screen, a DAVID framework that scores workflows on five tests: digital trace, cheap verification, bounded consequence, repetition, and value alignment. Applied to ten common workflows, the screen favors document-heavy coordination work such as RFIs, submittals, and field reports, and ranks prediction and autonomy lowest for now.

The problem: a large industry that has not become more productive

Construction is one of the largest sectors in the world economy, with about $13 trillion of gross output in 2023 (McKinsey, 2024). Its productivity record is weak. McKinsey estimates that global construction labor productivity grew about 0.4 percent a year between 2000 and 2022, against 2 percent for the total economy and 3 percent for manufacturing (McKinsey, 2024). Its earlier study reached a similar conclusion over a different period: 1 percent a year in construction, 2.8 percent for the world economy (McKinsey Global Institute, 2017).

The labor market makes the gap harder to close. In the 2025 Workforce Survey from the Associated General Contractors of America (AGC) and NCCER, about 92 percent of firms with openings reported difficulty filling hourly craft positions, and the same share reported difficulty filling salaried positions (AGC, 2025). Construction also carries a heavy safety burden: it recorded 1,034 fatal work injuries in the United States in 2024, the most of any private industry (BLS, 2026).

Information quality is a recurring cost driver. A 2021 Autodesk and FMI study, based on a survey of more than 3,900 professionals, estimated that decisions made on "bad data" accounted for about 14 percent of all rework in 2020 (Autodesk and FMI, 2021). That figure is a model built on survey responses and published by a software vendor, so it indicates direction rather than precise size.

What the evidence says about AI in construction today

Adoption is mostly exploration. RICS's 2025 survey found 45 percent of respondents reporting no AI implementation, 34 percent in early pilots, just under 12 percent using AI regularly in specific processes, 1.5 percent using it across multiple processes, and under 1 percent with organization-wide use (RICS, 2025). Most respondents were in the UK, and only 10 percent came from the Americas, so the U.S. picture may differ. The most cited barriers were lack of skilled personnel (46 percent), integration with existing systems (37 percent), and data quality and availability (30 percent). Respondents expected the largest future impact in design optioneering (40 percent) (RICS, 2025).

The industry is cautiously positive. In the AGC survey, 45 percent of firms said AI and robotics would positively affect construction jobs by automating manual, error-prone tasks, 32 percent expected no effect, and 12 percent expected job losses over five years (AGC, 2025).

Coordination paperwork is large and measurable. The best public dataset on requests for information (RFIs) is old but specific. Navigant's 2013 analysis of 1,362 projects and 1,083,807 RFIs from the Aconex platform found an average of 796 RFIs per project and a median reply time of 9.7 days. Based on interviews with three design and construction management firms, Navigant estimated about eight hours of administrative and technical effort per RFI, or roughly $1,080 each, implying about $860,000 per average project (Navigant Construction Forum, 2013). The cost estimate is informal and in 2013 dollars, but the volume data is drawn from platform records.

Field perception works in research, with conditions. A 2026 systematic review of 297 publications on digital safety monitoring and inspection found that adoption in practice "remains uneven" and that constraints cluster around technical reliability, organizational readiness, and governance, with workflow integration as the cross-cutting challenge (Le, Lin and Cheung, Journal of Management in Engineering, 2026). Progress-monitoring researchers report a similar gap: computer vision approaches depend on building models at the right level of development and on schedules that are detailed and current, which many projects lack (Núñez-Morales, Jung and Golparvar-Fard, ISARC, 2024).

Language models can read codes, but not reliably enough to sign. On 171 difficult building-code interpretation questions drawn from South Korean regulatory inquiries, the best method in a 2025 Automation in Construction study reached 63.2 percent accuracy, against 60.2 percent for Claude 3.7 alone; on a simpler question set, accuracy was about 80 percent (Lee and Lee, 2025). That is useful for triage and drafting, and well short of what an engineer of record can rely on.

Original framework: the Construction Workflow Screen

This is a DAVID-proposed framework. It has not been externally validated. Scores below are DAVID judgment based on the evidence above and are meant to be re-scored for a specific firm.

The evidence points to a pattern: AI performs best where work already leaves a digital record, a qualified person can check the output quickly, and a mistake is caught before it becomes concrete, steel, or an injury. Construction adds a fifth condition other industries can often ignore. Value is spread across owners, designers, general contractors, and subcontractors under separate contracts, so the party that pays for a tool is often not the party that saves money. McKinsey's 2017 study made a related point about the industry generally: it is highly fragmented, and "contracts have mismatches in risk allocations and rewards" (McKinsey Global Institute, 2017).

Score each workflow 0, 1, or 2 on five tests:

  1. Digital trace. Does the workflow already produce structured or semi-structured digital records (logs, specifications, models, photos with location)?
  2. Cheap verification. Can a qualified person check the output in a small fraction of the time it takes to produce it?
  3. Bounded consequence. Is an error caught before it becomes physical, contractual, or a safety event?
  4. Repetition. Does the workflow recur at high volume across projects?
  5. Value alignment. Does the organization that deploys and pays for the system capture most of the benefit?

A score of 8 to 10 suggests deploying with measurement; 6 or 7 suggests a pilot under representative site conditions; 5 or below suggests watching the research rather than funding production.

WorkflowTraceVerifyConsequenceRepetitionAlignmentTotalIndication
Field reports from voice, photos, and notes121228Deploy and measure
RFI triage, routing, and draft responses221218Deploy and measure
Submittal check against specifications211217Pilot
Contract, specification, and code review in preconstruction211127Pilot
Progress monitoring from reality capture112217Pilot
Safety monitoring with computer vision110226Pilot with strict limits
Quantity takeoff and estimating110226Pilot with strict limits
Design optioneering101114Watch
Schedule delay and cost-overrun prediction001124Watch
Autonomous site robotics010113Watch
FIG. 1 / THE CONSTRUCTION WORKFLOW SCREEN DAVID JUDGMENT, RE-SCORE FOR YOUR FIRM DIGITAL TRACE CHEAP VERIFY BOUNDED CONSEQ. REPE- TITION VALUE ALIGN TOTAL INDICATION Field reports from voice, photos, and notes 8 Deploy and measure RFI triage, routing, and draft responses 8 Deploy and measure Submittal check against specifications 7 Pilot Contract, specification, and code review in preconstruction 7 Pilot Progress monitoring from reality capture 7 Pilot Safety monitoring with computer vision 6 Pilot with strict limits Quantity takeoff and estimating 6 Pilot with strict limits Design optioneering 4 Watch Schedule delay and cost-overrun prediction 4 Watch Autonomous site robotics 3 Watch 2 YES 1 PARTLY 0 NO 8 TO 10 DEPLOY WITH MEASUREMENT / 6 OR 7 PILOT / 5 OR BELOW WATCH
FIG. 1 / THE CONSTRUCTION WORKFLOW SCREEN DAVID JUDGMENT, RE-SCORE FOR YOUR FIRM CRITERIA: 1 DIGITAL TRACE 2 CHEAP VERIFY 3 BOUNDED CONSEQ. 4 REPETITION 5 VALUE ALIGN Field reports from voice, photos, and notes 1 2 3 4 5 = 8 DEPLOY AND MEASURE RFI triage, routing, and draft responses 1 2 3 4 5 = 8 DEPLOY AND MEASURE Submittal check against specifications 1 2 3 4 5 = 7 PILOT Contract, specification, and code review in preconstruction 1 2 3 4 5 = 7 PILOT Progress monitoring from reality capture 1 2 3 4 5 = 7 PILOT Safety monitoring with computer vision 1 2 3 4 5 = 6 PILOT WITH STRICT LIMITS Quantity takeoff and estimating 1 2 3 4 5 = 6 PILOT WITH STRICT LIMITS Design optioneering 1 2 3 4 5 = 4 WATCH Schedule delay and cost-overrun prediction 1 2 3 4 5 = 4 WATCH Autonomous site robotics 1 2 3 4 5 = 3 WATCH 2 YES 1 PARTLY 0 NO 8 TO 10 DEPLOY WITH MEASUREMENT / 6 OR 7 PILOT / 5 OR BELOW WATCH
Figure 1DAVID's illustrative scores for ten common construction workflows. The two highest-scoring workflows are cheap to check and recur at high volume across projects.Source: DAVID AI. A DAVID-proposed framework; it has not been externally validated. Scores are DAVID judgment.

Three results stand out.

First, the paperwork scores highest. RFIs, submittals, and daily reports are text and image workflows with existing digital trails, high volume, and a professional who already reviews every item. AI can classify, route, find the relevant specification section, and draft, while the designer or project manager still decides.

Second, safety is high value but scores in the middle. A missed hazard is the most expensive error in the industry, and a system that is right most of the time can create false confidence. The 2026 review's advice applies: pilot under representative conditions and define who acts on each alert before scaling (Le, Lin and Cheung, 2026).

Third, the use case respondents expect most scores low. RICS respondents named design optioneering as the area of greatest expected impact (RICS, 2025). The screen ranks it near the bottom today because evaluating a design option is slow, expert work and the value is split between designer and owner. That is a judgment about near-term deployment, not about long-term potential.

Illustrative economics: AI-assisted RFI handling

Hypothetical inputs, using Navigant's 2013 cost structure. Not a benchmark and not client data.

Navigant's estimate splits each RFI into about four administrative hours at a median $82 per hour and four technical hours at $188 per hour (Navigant Construction Forum, 2013). Suppose an AI system halves administrative time (logging, classification, routing, finding the governing drawing and specification) and cuts technical time by a quarter through drafted responses that a designer edits.

MeasureResult
Baseline cost per RFI$1,080
Administrative saving (2 hours at $82)$164
Technical saving (1 hour at $188)$188
Gross saving per RFI$352
Gross saving per average project (796 RFIs)about $280,000
FIG. 2 / AI-ASSISTED RFI HANDLING ILLUSTRATIVE, HYPOTHETICAL INPUTS PER REQUEST FOR INFORMATION Baseline cost per RFI (4 admin hours at $82, 4 technical hours at $188) $1,080 Administrative saving (2 hours at $82) $164 Technical saving (1 hour at $188) $188 Gross saving per RFI $352 AVERAGE PROJECT OF 796 RFIS: ABOUT $280,000 GROSS SAVING
FIG. 2 / AI-ASSISTED RFI HANDLING ILLUSTRATIVE, HYPOTHETICAL INPUTS PER REQUEST FOR INFORMATION Baseline cost per RFI (4 admin hours at $82, 4 technical hours at $188) $1,080 Administrative saving (2 hours at $82) $164 Technical saving (1 hour at $188) $188 Gross saving per RFI $352 AVERAGE PROJECT OF 796 RFIS: ABOUT $280,000 GROSS SAVING
Figure 2Illustrative only. Hypothetical time savings applied to Navigant's 2013 cost structure. The saving is gross; it becomes value only if the freed hours are redeployed.Source: DAVID AI calculation using the cost structure from Navigant Construction Forum, 2013.

Before counting this as value, apply the four terms from DAVID's investment model in The Economics of Enterprise AI (capture, review, escaped errors, production probability). Construction adds one more question: who keeps the saving? Under design-bid-build, much of the technical effort sits with the design team, often on a fixed fee, while the contractor and owner bear the cost of slow answers. A faster median reply may be worth more to the owner's schedule than the hours are worth to the designer. Contracts and incentives, not model capability, may decide whether this workflow is adopted.

Implications for executives

  1. Start with the document layer. RFIs, submittals, field reports, and specification review score highest on the screen and keep a licensed professional in the decision.
  2. Fix information flow before prediction. Delay and cost forecasting depends on schedule and cost data that many projects do not keep current. Clean, structured project records are a prerequisite, and they pay off even without AI.
  3. Treat safety systems as aids to inspectors, not replacements. Define who acts on each alert, measure false negatives on site, and keep existing inspection practice in place.
  4. Price value alignment into contracts. Owners who want faster RFI turnaround or better progress data can specify data formats, response-time targets, and tool access in contracts rather than expecting one party to fund benefits that accrue to another.
  5. Re-score annually. Model capability, capture hardware, and data practice are moving. A workflow in "watch" today may move to "pilot" within a year.

Counterarguments and limitations

Large contractors with integrated design and build teams face less value fragmentation and may score workflows higher on alignment. Some vendors report strong results in progress monitoring and estimating; this article relies on peer-reviewed and public sources rather than vendor claims, which may understate what leading firms already achieve. The RFI data is from 2013 and the cost figures came from three firms. The RICS survey is weighted toward the UK and toward surveying professionals. The screen's equal weighting is a simplification, and a single safety-critical failure can outweigh every other score.

Conclusion

AI's near-term value in construction lies mostly in coordination: the questions, approvals, and records that move between parties before anything is built. Those workflows already leave digital trails, are reviewed by accountable professionals, and recur by the hundreds on every project. Safety, estimating, and progress monitoring deserve disciplined pilots. Prediction, generative design, and autonomy deserve attention, but not production budgets, until data practice and evidence catch up.

Methodology

Method. Research used live web sources on November 22, 2026. Every cited page was opened that day, and figures were checked against primary documents where available. DAVID AI conducted no survey, site study, or client measurement for this article. External findings are reported as published. The Construction Workflow Screen, its scores, and the RFI example are DAVID analysis; the example uses hypothetical improvement rates applied to Navigant's published cost structure.

Limitations. Survey figures are self-reported. The Autodesk and FMI estimate is a vendor-sponsored model. Navigant's RFI cost estimate is informal and dated. Academic results on code interpretation and computer vision come from specific datasets and may not transfer to a given project. Workflow scores are judgments, not measurements.

Disclosure. DAVID AI designs and builds production AI systems and has commercial partnerships with several AI technology providers, including some whose products are referenced in this article.

Related research. The Economics of Enterprise AI: How Executives Should Evaluate Investments describes the Risk-Adjusted Workflow Value model referenced above.

Sources

  1. McKinsey & Company, "Delivering on construction productivity is no longer optional," August 9, 2024.
  2. McKinsey Global Institute, "Reinventing construction through a productivity revolution," February 27, 2017.
  3. Associated General Contractors of America and NCCER, "2025 Workforce Survey Results: National Results," August 2025. Link
  4. U.S. Bureau of Labor Statistics, "Fatal work injuries declined in 2024," The Economics Daily, April 28, 2026. Link
  5. Autodesk and FMI, "Study from Autodesk and FMI Finds Better Data Strategies Could Save the Global Construction Industry $1.85 Trillion," September 14, 2021. Link
  6. Sawhney, A., and Pitman, K., "RICS artificial intelligence in construction report 2025," RICS, September 12, 2025. Link
  7. Navigant Construction Forum, "Impact & Control of RFIs on Construction Projects," April 2013 (hosted by CMAA). Link
  8. Le, P.-L., Lin, J. J., and Cheung, C., "Digital Safety Monitoring and Inspection in Construction: A Systematic Review of Deployment Readiness and Adoption Barriers," Journal of Management in Engineering 43(1), published online October 26, 2026. Link
  9. Núñez-Morales, J. D., Jung, Y., and Golparvar-Fard, M., "Evaluation of Mapping Computer Vision Segmentation from Reality Capture to Schedule Activities for Construction Monitoring in the Absence of Detailed BIM," ISARC 2024. Link
  10. Lee, J., and Lee, G., "Long context window-based zero-shot legal interpretation of building codes and regulations," Automation in Construction 179, November 2025. Link